MIL-I-81987(AS)
4.
QUALITY ASSURANCE PROVISIONS
4.1
Responsibility for Inspection - Unless otherwise specified in the
contract or purchase order, the supplier is responsible for the performance of all inspection
requirements as specified herein. Except as otherwise specified, the supplier may utiIize
his own facilities or any commercial laboratory acceptable to the Government. The
Government reserves the right to perform any inspections deemed necessary to assure
supplies and services conform to prescribed requirements.
4.1.1
Classification of Tests - Items covered by this specification shall
be subjected to the following tests to determine compliance with all applicable
requirements:
First Article (preproduction) tests
Initial production tests
Acceptance tests
Life test
4.2
First Article (Preproduction) Tests - First article (reproduction)
tests shall be made on an equipment representative of the production equipments to be
supplied under the contract. The tests shall be accomplished under the responsibility of
the contractor and shall be conducted in accordance with the approved test procedure
of 4.6. The government inspector and the procuring activity shall be advised when tests
are to be conducted so that a representative may be designated to witness or supervise
the tests when so desired. Contractors not having adequate facilities to conduct all
required tests shall obtain i-he services of a commercial testing laboratory acceptable to
the Government.
4.2.1
First Article (Reproduction) Test Data - The contractor shall submit
all data collected in conducting these tests to the procuring agency for review and approval.
On first production contracts this data shall include a list of all electrical and electronic
parts giving their specified voltage, and ambient and surface temperatures. The ambient
and surface temperature shall be obtained under the extreme high temperature operating
condition.
4.2.2
Scope of Tests - Preproduction tests shall include all tests deemed
necessary by the procuring activity to determine that the equipment meets alI the require-
ments of this specification and the contract. Preproduction tests shall include environ-
mental and interference tests. Environmental tests shall consist only of Temperature-
Altitude, Vibration, Humidity, Salt Fog, and Shock tests and shall be conducted in
accordance with the requirements of Specification MIL-T-5422 (Except humidity will be
maximum temperature) and limits specified in Specification MIL-T-21200.
limited to
Interference tests shall be conducted in accordance with MIL-STD-462 to the requirements
of MIL-STD-461.